This is the first of our monthly construction updates. Please see the summary below and pictures at
the bottom of this post! We’re happy to
be finally underway!
SITE WORK:
Clearing, grubbing and chipping of clearing debris is complete.
Erosion control work is 70% complete with a double layer of silt fence
installed around the perimeter of the site, tree‐save fence installed, rip rap
check dams installed at the detention pond outfall and a construction entrance
installed along the north side of the project site.
Mass grading work is 80% complete. A significant amount of
cut and fill work has been completed throughout the site to the point where
detention ponds are generally to grade and the building pad is at sub‐grade.
Excavation for the gravity stacked pre‐cast retaining wall along the northern
boundary of the site has been completed, and drives/parking bay areas are around
70% to subgrade. As part of the grading process, construction of a gabion
retaining wall has been completed to define a portion of the primary storm
drain pond located along the south side of the property. The only other site
retaining wall will be located along the north property line where excavation
work has been completed and a portion of the pre‐cast concrete wall panels have
been delivered to the project site. Retaining wall construction is 40%
complete.
Construction of site infrastructure improvements is around
65% complete. Installation of sanitary sewer main, outfall and service laterals
is complete and tie‐in of the onsite sewer to the municipal main has been completed.
Additionally, installation of the primary storm drainage system is 85%
complete. The majority of onsite storm drainage is now in place, with pre‐cast
inlet basins and piping installed within the interior areas of the site and piped
to the onsite detention basins. Installation of the drainage along the east
property line, where the main entrance from Oakland Park Boulevard is located,
is currently in progress. Installation of the water distribution system has not
yet commenced.
STRUCTURES:
Construction of the building structure has recently
commenced. The initial layout work has been completed and installation of
under‐slab plumbing and the elevator pit is currently in progress. Under‐slab
plumbing work is 65% complete, which would translate to the plumbing line item
being around 15% complete overall. Installation of the elevator pit is around 50%
complete. The concrete footing/pad was noted to be in place and formwork for
the pit walls has been completed. It appears that the pit walls will be poured
upon the subcontractor’s return to the site. In addition to the elevator pit,
reinforcing steel and formwork lumber for the building slab was observed to be
onsite. Concrete construction is around 5% complete.
We want to ensure the community stays up to date with the
plans and progress of our development.
As such, if you have any questions or would like to send us a comment
regarding Evermore, please either post a comment on the blog or send us an
email at info@peachtreehousing.com. Please use this email for questions or
comments regarding the development process only. For information regarding pre-leasing, please
email evermoresrvillage@fairwaymanagement.com.
Please visit this blog often as we will be posting updated
pictures and blogs throughout the construction of Evermore Senior Village.
Silt and tree‐save fencing installed
Construction entrance established
Site clearing and grubbing complete; topsoil stockpiled onsite
Building pad placed to subgrade
Sewer service laterals installed to building pad
Elevator pit slab placed and formwork completed for pit walls