Construction update #4 is below. Please see the summary and pictures at the
bottom of this post!
SITE WORK:
2018, the winter that never ends! Unfortunately, the weather has delayed us and
current activities are focused on the installation of the binder surface of
asphalt along the interior drives and parking bays. Work on this component of
the project is underway but is limited due to wet soil conditions. We are blading
wet soils to aid in the drying process.
As for site work completed to date, mass grading work is now
complete along with installation of site infrastructure including sanitary
sewer, storm drainage and water distribution. Additionally, construction of all
retaining walls has been completed and sleeves have been installed in select
locations under interior drives. Installation of curb and gutter is 80%
complete with the majority of curb now in place. Installation of graded aggregate
base has been completed in limited quantity and is generally limited to the
east side of the 3-story building structure. Paving base is estimated to be 25%
in place. Assuming weather conditions slightly improve, we project the binder
surface of asphalt could be placed within 2 weeks which would allow vertical
construction to commence.
STRUCTURES:
Building construction has continued to progress and is now
underway at both Buildings 100 and 200. At Building 100, installation of all
under-slab plumbing and electrical piping, elevator pits and the foundation
wall along the west elevation of the building has been completed and concrete
slab placement is also now complete. At Building 200, under-slab plumbing
rough-in work has been completed. As soon as soil conditions improve,
foundation/concrete slab placement will begin at this building structure. To
date, plumbing work is 25 to 30% complete, electrical work around 15% complete
and concrete placement around 80% complete.
We want to ensure the community stays up to date with the
plans and progress of our development.
As such, if you have any questions or would like to send us a comment
regarding Evermore, please either post a comment on the blog or send us an
email at info@peachtreehousing.com. Please use this email for questions or comments
regarding the development process only.
For information regarding pre-leasing, please email evermoresrvillage@fairwaymanagement.com.
Please visit this blog often as we will be posting updated
pictures and blogs throughout the construction of Evermore Senior Village.
Curb and gutter placement approximately 80% complete:
Curb and gutter placement approximately 80% complete:
A limited amount of graded aggregate base installed along east side of Building 100:
Retaining wall construction and backfilling completed:
East/West section of Building 100 slab placed this period:
North/South section of Building 100 slab installed:
Under-slab plumbing completed at Building 200: