Construction Update #9


Construction update #9 is below.  Please see the summary and pictures at the bottom of this post! 

SITE WORK:
Fine grading and sidewalk construction had been completed around Building 200 and fine grading completed around Building 100 where masonry finishes are complete. Placement of all concrete handicap parking spaces is now complete and masonry work at the dumpster enclosure has commenced. Fine grading work is 50% complete and site concrete is 80% complete.

STRUCTURES:
Construction related to the building structures is nearing substantial completion. Under-slab utilities, concrete foundations, elevator pits and concrete slab construction is substantially complete. Rough carpentry work is 99% complete and framing on the Porte Cochère is underway.  Window and patio door installations have been completed at each building, shingle roofing is complete at Building 200 and the maintenance building and TPO membrane roofing is roughly 95% complete.

MEP rough-in appears is nearing substantial completion and drywall pre-hangs and gypcrete pre-pours are substantially complete. MEP rough-in at the ground floor is wrapping up with final punch out work underway. Wall insulation is complete at the 4th floor of Building 100 and materials were partially stocked on the 3rd floor with installation just beginning. Overall, electrical work and plumbing work is estimated to be around 70% complete, fire sprinkler work around 90% complete and HVAC around 65% complete.

FINISHES & QUALITY
Both interior and exterior finishes are now underway with exterior finishes further progressed than interior finishes. At the building exteriors, masonry veneer and siding work has been completed at Building 200, masonry work is complete at the maintenance building and masonry and siding work is currently underway at Building 100. Masonry work is 85 to 90% complete and siding approximately 65% at Building 100. Overall, masonry work is estimated to be 95% complete and siding installation roughly 70 to 75% complete.

Interior finishes have just recently commenced and are limited to drywall. Drywall installation is underway at the 4th floor of Building 100. Inclusive of drywall pre-hangs, drywall installation is estimated to be 30% complete.

We want to ensure the community stays up to date with the plans and progress of our development.  As such, if you have any questions or would like to send us a comment regarding Evermore, please either post a comment on the blog or send us an email at info@peachtreehousing.com.  Please use this email for questions or comments regarding the development process only.  For information regarding pre-leasing, please email evermoresrvillage@fairwaymanagement.com.

Please visit this blog often as we will be posting updated pictures and blogs throughout the construction of Evermore Senior Village.


Structural steel and concrete paving installed for Porte Cochère at Building 100

View of east elevation of north/south wing of Building 100

Framing, roofing and masonry work completed at maintenance shed

View of west elevation of north/south wing of Building 100

Plumbing rough-in complete at Building 100

Drywall installation underway at 4th floor of Building 100

Roofing, brick and siding completed at Building 200