Friday, August 31, 2018

Construction Update #9


Construction update #9 is below.  Please see the summary and pictures at the bottom of this post! 

SITE WORK:
Fine grading and sidewalk construction had been completed around Building 200 and fine grading completed around Building 100 where masonry finishes are complete. Placement of all concrete handicap parking spaces is now complete and masonry work at the dumpster enclosure has commenced. Fine grading work is 50% complete and site concrete is 80% complete.

STRUCTURES:
Construction related to the building structures is nearing substantial completion. Under-slab utilities, concrete foundations, elevator pits and concrete slab construction is substantially complete. Rough carpentry work is 99% complete and framing on the Porte Cochère is underway.  Window and patio door installations have been completed at each building, shingle roofing is complete at Building 200 and the maintenance building and TPO membrane roofing is roughly 95% complete.

MEP rough-in appears is nearing substantial completion and drywall pre-hangs and gypcrete pre-pours are substantially complete. MEP rough-in at the ground floor is wrapping up with final punch out work underway. Wall insulation is complete at the 4th floor of Building 100 and materials were partially stocked on the 3rd floor with installation just beginning. Overall, electrical work and plumbing work is estimated to be around 70% complete, fire sprinkler work around 90% complete and HVAC around 65% complete.

FINISHES & QUALITY
Both interior and exterior finishes are now underway with exterior finishes further progressed than interior finishes. At the building exteriors, masonry veneer and siding work has been completed at Building 200, masonry work is complete at the maintenance building and masonry and siding work is currently underway at Building 100. Masonry work is 85 to 90% complete and siding approximately 65% at Building 100. Overall, masonry work is estimated to be 95% complete and siding installation roughly 70 to 75% complete.

Interior finishes have just recently commenced and are limited to drywall. Drywall installation is underway at the 4th floor of Building 100. Inclusive of drywall pre-hangs, drywall installation is estimated to be 30% complete.

We want to ensure the community stays up to date with the plans and progress of our development.  As such, if you have any questions or would like to send us a comment regarding Evermore, please either post a comment on the blog or send us an email at info@peachtreehousing.com.  Please use this email for questions or comments regarding the development process only.  For information regarding pre-leasing, please email evermoresrvillage@fairwaymanagement.com.

Please visit this blog often as we will be posting updated pictures and blogs throughout the construction of Evermore Senior Village.


Structural steel and concrete paving installed for Porte Cochère at Building 100

View of east elevation of north/south wing of Building 100

Framing, roofing and masonry work completed at maintenance shed

View of west elevation of north/south wing of Building 100

Plumbing rough-in complete at Building 100

Drywall installation underway at 4th floor of Building 100

Roofing, brick and siding completed at Building 200


Thursday, August 2, 2018

Construction Update #8


Construction update #8 is below.  Please see the summary and pictures at the bottom of this post! 

SITE WORK:
Installation of sidewalks has occurred along the frontage of Building 200 and additional concrete paving has been completed at handicap parking spaces. To date, site concrete is 75% complete inclusive of walks and paved surfaces.

Further progress, with regard to site work, is expected to be minimal until exterior finishes are completed at Building 100. As exterior building finishes are completed, installation of site finishes such as sidewalks, landscaping/irrigation and paving will resume.

STRUCTURES:
Construction related to the building structures has continued to progress and is now approaching completion. Under-slab utilities, concrete foundations, elevator pits and concrete slab construction, rough carpentry, stair systems and building dry-in is now substantially complete. Over the past several weeks, dry-in work has been completed at Building 100 which includes installation of patio doors, windows and shingle roofing.

Rough framing including all wood framing elements, blocking and installation of structural hardware is substantially complete. Project staff reports installation of rough framing hardware has been completed in recent weeks and the majority of framing punch list items has been completed.

Building dry-in work, (roofing, windows, exterior doors), has further progressed and is now between 90 and 95% complete. At Building 100, installation of shingle roofing, windows and exterior patio doors have been completed. Installation of membrane roofing over flat/low slope roof areas and installation of hollow metal doors and aluminum/glass doors at common entry points remains to be completed. At Building 200, all roofing, windows and exterior door systems have been installed.
MEP rough-in, drywall pre-hangs, gypcrete pre-pours and installation of steel stair systems is nearing completion. At Building 100, drywall pre-hangs, gypcrete pre-pours, fire sprinkler rough-in and HVAC rough-in is complete. Steel stair systems are 90% complete with only pre-cast tread installation remaining to be completed. Plumbing rough-in is 90% complete with all waste and water piping installed and only tub/shower installations remaining to be completed. Electrical rough-in is 65% complete with the 3rd and 4th floor rough-in substantially complete and rough-in work occurring on the 1st and 2nd floors. Overall, electrical work is around 55 to 60% complete, plumbing is 60 to 65% complete, fire sprinkler work is approximately 90% complete and HVAC is around 60% complete.

FINISHES & QUALITY
At Building 100, installation of brick veneer was underway and is 30 to 35% complete. Siding installation has not yet commenced. At Building 200, installation of brick veneer and siding is complete. Overall, brick installation is estimated to be 50% complete and siding installation roughly 25% complete.

We want to ensure the community stays up to date with the plans and progress of our development.  As such, if you have any questions or would like to send us a comment regarding Evermore, please either post a comment on the blog or send us an email at info@peachtreehousing.com.  Please use this email for questions or comments regarding the development process only.  For information regarding pre-leasing, please email evermoresrvillage@fairwaymanagement.com.

Please visit this blog often as we will be posting updated pictures and blogs throughout the construction of Evermore Senior Village.

Brick installation nearing completion on south elevation of east/west wing of Building 100


Pressure treated material recommend where wood framing intersects masonry veneer on Building 100

Waste and water line rough-in complete at Building 100

Electrical rough-in underway at Building 100

Brick and siding installation complete at Building 200

Concrete sidewalks placed at Building 200

Brick installation complete on west elevation of east/west wing of Building 100

Construction Update #10

Construction update #10 is below.   Please see the summary and pictures at the bottom of this post!   SITE WORK: Sidewalks and flat ...