Friday, October 19, 2018

Construction Update #10


Construction update #10 is below.  Please see the summary and pictures at the bottom of this post! 

SITE WORK:
Sidewalks and flat concrete work is approximately 80% complete with work ongoing. Over the next 7 to 10 days, we anticipate all remaining concrete flatwork will be completed. To date, fine grading work is 75% complete and site concrete approximately 90 to 95% complete. In addition to the concrete flat work, installation of the chain link fence around the detention pond has commenced. Installation of steel post is underway and fence fabric is onsite. Site fencing is estimated to be 40% complete.

STRUCTURES:
Construction related to the building structures continues to progress and is now substantially complete. Under-slab utilities, concrete foundations, elevator pits, concrete slab construction, rough carpentry, steel stair installation and dry-in work are complete. A limited amount of roofing work remains to be completed and includes installation of standing seam metal roof accents and metal coping at TPO membrane roof areas.

MEP rough-in, drywall pre-hangs and gypcrete pre-pours is also substantially complete. Overall, plumbing work is around 70% complete, fire sprinkler work 90% complete, electrical 80% complete and HVAC around 65% complete.

FINISHES & QUALITY
Both interior and exterior finishes have continued to progress at each building. At Building 100, installation of masonry veneer is substantially complete and siding installation was approximately 98% complete. A limited amount of siding/exterior trim work remains to be completed at the Porte Cochere. Installation of hollow metal doors has also been completed and storefront entry doors at the main entrance should be installed in the near future. At the interior of Building 100, drywall installation and finishing is 75% complete, gypcrete flooring is now 100% complete, interior painting is 30% complete and interior doors and trim are roughly 25 to 30% complete. Cabinetry and countertops were also noted to be in place within the 4th floor units and cabinetry is roughly 20 to 25% complete.

At Building 200, exterior building finishes are 90% complete. Masonry, siding, soffits and exterior trims have been completed and exterior painting is approximately 80% complete. Installation of gutters and downspouts has also been completed. Unit interior finishes are similarly complete at units along the 4th floor of Building 100. Drywall, interior doors and trim, cabinetry and countertop installations are substantially complete. Interior ceilings have been painted and wall priming has been completed. Interior painting is estimated to be 40 to 45% complete.

We want to ensure the community stays up to date with the plans and progress of our development.  As such, if you have any questions or would like to send us a comment regarding Evermore, please either post a comment on the blog or send us an email at info@peachtreehousing.com.  Please use this email for questions or comments regarding the development process only.  For information regarding pre-leasing, please email evermoresrvillage@fairwaymanagement.com.

Please visit this blog often as we will be posting updated pictures and blogs throughout the construction of Evermore Senior Village.

Framing and masonry work complete at Porte Cochere

Heat pump concrete pads 80% complete at Building 200

View of south elevation of north/south wing of Building 100

View of south elevation of east/west wing of Building 100

Drywall, gypcrete, paint prime, interior doors and wood trim installed in 4th floor units at Building 100

Cabinetry and countertops installed in 4th floor units at Building 100

Drywall hung in 2nd floor corridor at Building 100

MEP rough-in complete on 1st floor at Building 100

Gutter installation complete at Building 200

Chain link fence installation underway around detention pond