SITE WORK:
Mass grading work is 98% complete. Grading work throughout
the site is generally complete with the exception of the building pad for
Building 200 where import of structural fill material was nearing completion.
Excavation and shaping of detention ponds, placement of fill on interior drives
and parking bays, construction of the building pad for building 100 and
construction and backfilling of the MSE/Gabion retaining wall and gravity retaining
wall have been completed. Compaction of soils in the parking lot south of
Building 100 is nearly complete and construction of the building pad for
building 200 is underway. Several more additional loads of import fill were
required at building 200 prior to grading work.
Construction of site infrastructure improvements is substantially
complete including all sanitary sewer, storm drainage and water distribution
components.
Construction of the interior drives and parking lots has not
commenced but staking for the curb and gutter system is throughout the site.
Curb and gutter work is scheduled to commence the week of 02/26 pending
appropriate weather conditions.
STRUCTURES:
Building construction has continued to progress and remains
isolated to Building 100. Installation of under-slab plumbing and electrical
piping, elevator pits and the foundation wall along the west elevation of the
building has been completed. Concrete slab placement has occurred along the
north/south wing of the building through the main lobby area. Approximately 60%
of the slab-on-grade for Building 100 has been placed and around 50% of all
concrete slab placement is now complete. Overall, plumbing work is estimated to
be 20% complete, electrical work 10% complete and concrete work approximately
50% complete.
We want to ensure the community stays up to date with the
plans and progress of our development.
As such, if you have any questions or would like to send us a comment
regarding Evermore, please either post a comment on the blog or send us an
email at info@peachtreehousing.com. Please use this email for questions or
comments regarding the development process only. For information regarding pre-leasing, please
email evermoresrvillage@fairwaymanagement.com.
Please visit this blog often as we will be posting updated
pictures and blogs throughout the construction of Evermore Senior Village.
Interior drives and parking bays appear to be at or close to sub-grade