Thursday, March 1, 2018

Construction Update #3


SITE WORK:
Mass grading work is 98% complete. Grading work throughout the site is generally complete with the exception of the building pad for Building 200 where import of structural fill material was nearing completion. Excavation and shaping of detention ponds, placement of fill on interior drives and parking bays, construction of the building pad for building 100 and construction and backfilling of the MSE/Gabion retaining wall and gravity retaining wall have been completed. Compaction of soils in the parking lot south of Building 100 is nearly complete and construction of the building pad for building 200 is underway. Several more additional loads of import fill were required at building 200 prior to grading work.

Construction of site infrastructure improvements is substantially complete including all sanitary sewer, storm drainage and water distribution components.

Construction of the interior drives and parking lots has not commenced but staking for the curb and gutter system is throughout the site. Curb and gutter work is scheduled to commence the week of 02/26 pending appropriate weather conditions.

STRUCTURES:
Building construction has continued to progress and remains isolated to Building 100. Installation of under-slab plumbing and electrical piping, elevator pits and the foundation wall along the west elevation of the building has been completed. Concrete slab placement has occurred along the north/south wing of the building through the main lobby area. Approximately 60% of the slab-on-grade for Building 100 has been placed and around 50% of all concrete slab placement is now complete. Overall, plumbing work is estimated to be 20% complete, electrical work 10% complete and concrete work approximately 50% complete.

We want to ensure the community stays up to date with the plans and progress of our development.  As such, if you have any questions or would like to send us a comment regarding Evermore, please either post a comment on the blog or send us an email at info@peachtreehousing.com.  Please use this email for questions or comments regarding the development process only.  For information regarding pre-leasing, please email evermoresrvillage@fairwaymanagement.com.

Please visit this blog often as we will be posting updated pictures and blogs throughout the construction of Evermore Senior Village.


Interior drives and parking bays appear to be at or close to sub-grade

Gravity wall along the north side of the property has been completed

Construction of building pad for building 200 nearing completion

Foundation wall installed along west end of Building 100

Both elevator pits installed at Building 100

Concrete slab placed on north/south wing of Building 100

Storm drainage work completed under access drive from Oakland Parkway