Construction update #6 is below. Please see the summary and pictures at the
bottom of this post!
SITE WORK:
Over the last several weeks, site work construction has been
minimal as most of the initial site work activities have previously been
completed and the site is considered to be stabilized. As exterior building
finishes are completed, installation of site finishes such as sidewalks,
landscaping/irrigation and paving will resume.
STRUCTURES:
Construction related to the building structures has
continued to progress. Under-slab utilities, concrete foundations, elevator
pits and concrete slab construction is now complete. Rough framing work is in
progress at Building 100 where framing is 85 to 90% complete.
Framing on the 1st and 2nd floors is now substantially
complete and 3rd floor wall framing is approximately 80% complete. Installation
of roof trusses and roof decking has commenced and the roof system is roughly
40% complete. Installation of the exterior sheathing is underway and estimated
to be around 65% complete. At Building 200, rough framing work is substantially
complete and framing of the maintenance garage is substantially complete.
Overall, rough framing work is around 90% complete.
Installation of windows and roofing should commence prior to
the end of the month. Additionally, steel stair materials for Building 100 are on
site.
Plumbing rough-in has commenced with installation of waste
and water piping mostly complete at Building 200. Plumbing sub-contractor was
on site and mobilizing at Building 100 to begin rough-in activities. Plumbing
installations are estimated to be 40% complete.
We want to ensure the community stays up to date with the
plans and progress of our development.
As such, if you have any questions or would like to send us a comment
regarding Evermore, please either post a comment on the blog or send us an
email at info@peachtreehousing.com. Please use this email for questions or
comments regarding the development process only. For information regarding pre-leasing, please
email evermoresrvillage@fairwaymanagement.com.
Please visit this blog often as we will be posting updated
pictures and blogs throughout the construction of Evermore Senior Village.
View of east elevation of north/south wing of Building 100:
View of north elevation of east/west wing of Building 100:
View of west elevation of north/south wing of Building 100:
Roof truss installation underway at Building 100:
Rough framing substantially complete at Building 200: