Tuesday, May 15, 2018

Construction Update #5


Construction update #5 is below.  Please see the summary and pictures at the bottom of this post! 

SITE WORK:
Mass grading and installation of site infrastructure is now substantially complete. Final grading of detention basins, slopes and backfilling of most curb and gutter is also complete. As for site utilities, storm drainage, sanitary sewer and water distribution work is now complete throughout the site with services for domestic and fire water and sanitary sewer was evident to the building structures. Similarly, storm drainage inlets are throughout the property and piping extends to the detention basin areas.

Construction of interior roads and walks has also progressed. Curb and gutter installations is approximately 98% complete with curb now defining the interior drives and parking bays. A few curb tie-ins remain to be completed in select areas where equipment access is still required. Graded aggregate paving base has been installed throughout the property and asphalt paving work is now estimated to be 60% complete.

STRUCTURES:
Building construction has continued to progress with under-slab utilities, concrete foundations, elevator pits and concrete slab construction complete. Rough framing work is in progress at both Buildings 100 and 200. At Building 100, framing is substantially complete at the first floor walls and floor systems for the 2nd floor were in place. Wall framing at the 2nd floor is approximately 90% complete and exterior wall sheathing is roughly 25% complete for the entirety of the building. At Building 200, wall framing and exterior sheathing is substantially complete. Overall, rough framing work is 50-55% complete.

We want to ensure the community stays up to date with the plans and progress of our development.  As such, if you have any questions or would like to send us a comment regarding Evermore, please either post a comment on the blog or send us an email at info@peachtreehousing.com.  Please use this email for questions or comments regarding the development process only.  For information regarding pre-leasing, please email evermoresrvillage@fairwaymanagement.com.

Please visit this blog often as we will be posting updated pictures and blogs throughout the construction of Evermore Senior Village.


Rough framing underway at Building 100:

Curb and gutter placement approximately 98% complete and GAB placement substantially complete :

Backfilling and fine grading mostly complete and slope stabilization underway:

Installation of underground electricity nearing completion:

Exterior sheathing installation underway at Building 100:

Construction Update #10

Construction update #10 is below.   Please see the summary and pictures at the bottom of this post!   SITE WORK: Sidewalks and flat ...