Thursday, June 7, 2018

Construction Update #6


Construction update #6 is below.  Please see the summary and pictures at the bottom of this post! 

SITE WORK:
Over the last several weeks, site work construction has been minimal as most of the initial site work activities have previously been completed and the site is considered to be stabilized. As exterior building finishes are completed, installation of site finishes such as sidewalks, landscaping/irrigation and paving will resume.

STRUCTURES:
Construction related to the building structures has continued to progress. Under-slab utilities, concrete foundations, elevator pits and concrete slab construction is now complete. Rough framing work is in progress at Building 100 where framing is 85 to 90% complete.

Framing on the 1st and 2nd floors is now substantially complete and 3rd floor wall framing is approximately 80% complete. Installation of roof trusses and roof decking has commenced and the roof system is roughly 40% complete. Installation of the exterior sheathing is underway and estimated to be around 65% complete. At Building 200, rough framing work is substantially complete and framing of the maintenance garage is substantially complete. Overall, rough framing work is around 90% complete.

Installation of windows and roofing should commence prior to the end of the month. Additionally, steel stair materials for Building 100 are on site.

Plumbing rough-in has commenced with installation of waste and water piping mostly complete at Building 200. Plumbing sub-contractor was on site and mobilizing at Building 100 to begin rough-in activities. Plumbing installations are estimated to be 40% complete.

We want to ensure the community stays up to date with the plans and progress of our development.  As such, if you have any questions or would like to send us a comment regarding Evermore, please either post a comment on the blog or send us an email at info@peachtreehousing.com.  Please use this email for questions or comments regarding the development process only.  For information regarding pre-leasing, please email evermoresrvillage@fairwaymanagement.com.

Please visit this blog often as we will be posting updated pictures and blogs throughout the construction of Evermore Senior Village.


View of east elevation of north/south wing of Building 100:

View of north elevation of east/west wing of Building 100:

View of west elevation of north/south wing of Building 100:

Roof truss installation underway at Building 100:

Rough framing substantially complete at Building 200: