Thursday, August 2, 2018

Construction Update #8


Construction update #8 is below.  Please see the summary and pictures at the bottom of this post! 

SITE WORK:
Installation of sidewalks has occurred along the frontage of Building 200 and additional concrete paving has been completed at handicap parking spaces. To date, site concrete is 75% complete inclusive of walks and paved surfaces.

Further progress, with regard to site work, is expected to be minimal until exterior finishes are completed at Building 100. As exterior building finishes are completed, installation of site finishes such as sidewalks, landscaping/irrigation and paving will resume.

STRUCTURES:
Construction related to the building structures has continued to progress and is now approaching completion. Under-slab utilities, concrete foundations, elevator pits and concrete slab construction, rough carpentry, stair systems and building dry-in is now substantially complete. Over the past several weeks, dry-in work has been completed at Building 100 which includes installation of patio doors, windows and shingle roofing.

Rough framing including all wood framing elements, blocking and installation of structural hardware is substantially complete. Project staff reports installation of rough framing hardware has been completed in recent weeks and the majority of framing punch list items has been completed.

Building dry-in work, (roofing, windows, exterior doors), has further progressed and is now between 90 and 95% complete. At Building 100, installation of shingle roofing, windows and exterior patio doors have been completed. Installation of membrane roofing over flat/low slope roof areas and installation of hollow metal doors and aluminum/glass doors at common entry points remains to be completed. At Building 200, all roofing, windows and exterior door systems have been installed.
MEP rough-in, drywall pre-hangs, gypcrete pre-pours and installation of steel stair systems is nearing completion. At Building 100, drywall pre-hangs, gypcrete pre-pours, fire sprinkler rough-in and HVAC rough-in is complete. Steel stair systems are 90% complete with only pre-cast tread installation remaining to be completed. Plumbing rough-in is 90% complete with all waste and water piping installed and only tub/shower installations remaining to be completed. Electrical rough-in is 65% complete with the 3rd and 4th floor rough-in substantially complete and rough-in work occurring on the 1st and 2nd floors. Overall, electrical work is around 55 to 60% complete, plumbing is 60 to 65% complete, fire sprinkler work is approximately 90% complete and HVAC is around 60% complete.

FINISHES & QUALITY
At Building 100, installation of brick veneer was underway and is 30 to 35% complete. Siding installation has not yet commenced. At Building 200, installation of brick veneer and siding is complete. Overall, brick installation is estimated to be 50% complete and siding installation roughly 25% complete.

We want to ensure the community stays up to date with the plans and progress of our development.  As such, if you have any questions or would like to send us a comment regarding Evermore, please either post a comment on the blog or send us an email at info@peachtreehousing.com.  Please use this email for questions or comments regarding the development process only.  For information regarding pre-leasing, please email evermoresrvillage@fairwaymanagement.com.

Please visit this blog often as we will be posting updated pictures and blogs throughout the construction of Evermore Senior Village.

Brick installation nearing completion on south elevation of east/west wing of Building 100


Pressure treated material recommend where wood framing intersects masonry veneer on Building 100

Waste and water line rough-in complete at Building 100

Electrical rough-in underway at Building 100

Brick and siding installation complete at Building 200

Concrete sidewalks placed at Building 200

Brick installation complete on west elevation of east/west wing of Building 100