Construction update #8 is below. Please see the summary and pictures at the
bottom of this post!
SITE WORK:
Installation of sidewalks has occurred along the frontage of
Building 200 and additional concrete paving has been completed at handicap
parking spaces. To date, site concrete is 75% complete inclusive of walks and
paved surfaces.
Further progress, with regard to site work, is expected to
be minimal until exterior finishes are completed at Building 100. As exterior
building finishes are completed, installation of site finishes such as
sidewalks, landscaping/irrigation and paving will resume.
STRUCTURES:
Construction related to the building structures has
continued to progress and is now approaching completion. Under-slab utilities,
concrete foundations, elevator pits and concrete slab construction, rough
carpentry, stair systems and building dry-in is now substantially complete.
Over the past several weeks, dry-in work has been completed at Building 100
which includes installation of patio doors, windows and shingle roofing.
Rough framing including all wood framing elements, blocking
and installation of structural hardware is substantially complete. Project
staff reports installation of rough framing hardware has been completed in
recent weeks and the majority of framing punch list items has been completed.
Building dry-in work, (roofing, windows, exterior doors),
has further progressed and is now between 90 and 95% complete. At Building 100,
installation of shingle roofing, windows and exterior patio doors have been
completed. Installation of membrane roofing over flat/low slope roof areas and
installation of hollow metal doors and aluminum/glass doors at common entry
points remains to be completed. At Building 200, all roofing, windows and
exterior door systems have been installed.
MEP rough-in, drywall pre-hangs, gypcrete pre-pours and
installation of steel stair systems is nearing completion. At Building 100,
drywall pre-hangs, gypcrete pre-pours, fire sprinkler rough-in and HVAC
rough-in is complete. Steel stair systems are 90% complete with only pre-cast
tread installation remaining to be completed. Plumbing rough-in is 90% complete
with all waste and water piping installed and only tub/shower installations
remaining to be completed. Electrical rough-in is 65% complete with the 3rd and
4th floor rough-in substantially complete and rough-in work occurring on the
1st and 2nd floors. Overall, electrical work is around 55 to 60% complete,
plumbing is 60 to 65% complete, fire sprinkler work is approximately 90% complete
and HVAC is around 60% complete.
FINISHES & QUALITY
At Building 100, installation of brick veneer was underway
and is 30 to 35% complete. Siding installation has not yet commenced. At
Building 200, installation of brick veneer and siding is complete. Overall,
brick installation is estimated to be 50% complete and siding installation
roughly 25% complete.
We want to ensure the community stays up to date with the
plans and progress of our development.
As such, if you have any questions or would like to send us a comment
regarding Evermore, please either post a comment on the blog or send us an
email at info@peachtreehousing.com. Please use this email for questions or
comments regarding the development process only. For information regarding pre-leasing, please
email evermoresrvillage@fairwaymanagement.com.
Please visit this blog often as we will be posting updated
pictures and blogs throughout the construction of Evermore Senior Village.
Brick installation nearing completion on south elevation of east/west wing of Building 100
Pressure treated material recommend where wood framing intersects masonry veneer on Building 100
Waste and water line rough-in complete at Building 100
Electrical rough-in underway at Building 100
Brick and siding installation complete at Building 200
Concrete sidewalks placed at Building 200
Brick installation complete on west elevation of east/west wing of Building 100